Location
Essex
Client
DfE
Facility
SmartClass® Temporary school
No. of Modules
54
Installation to Completion
phase 1 10 Weeks | phase 2 16 weeks
Rental Period
104 weeks

Project
Summary
View Project Gallery
Hockley Primary School had a requirement for a temporary school after it was forced to close due to the detection of Reinforced Autoclaved Aerated Concrete (RAAC).
McAvoy was awarded the project due to its ability to meet the challenging programme and provide a high-quality solution that would benefit the staff and pupils. McAvoy delivered the two 2-storey buildings in two phases in order to meet the strict timelines and to ensure the pupils could return to the school as soon as phase 1 was completed.
View Project Gallery
Hear From
Academies Enterprise Trust